THE DIGITAL GARDENS OF THE NORTH TYNE VALLEY — V6 PHYSICAL MODEL NOTES
17 October 2026

CAPACITY RULE
Each active node is sized at exactly 4.46 kW of IT capacity per resident. The population basis is the latest official 2021 Census parish/town-council population available for each active community. Barrasford uses Chollerton parish and Chollerford uses Humshaugh parish as the smallest parish geographies covering those settlements.

COMMUNITY SCHEDULE
- Falstone: population 215; 0.95890 MW IT (display 0.96 MW)
- Bellingham: population 1,255; 5.59730 MW IT (display 5.60 MW)
- Wark: population 719; 3.20674 MW IT (display 3.21 MW)
- Barrasford: population 788; 3.51448 MW IT (display 3.51 MW)
- Chollerford: population 711; 3.17106 MW IT (display 3.17 MW)
- Haydon Bridge: population 2,374; 10.58804 MW IT (display 10.59 MW)
- Hexham: population 11,346; 50.60316 MW IT (display 50.60 MW)
- Corbridge: population 3,558; 15.86868 MW IT (display 15.87 MW)

TOTAL
Population: 20,966
IT capacity: 93.50836 MW
Capacity intensity: 4.46 kW/resident

CENTRAL OPERATIONAL MODEL
Project electricity: 854.069 GWh/year
Unmatched grid imports: 85.407 GWh/year
Useful recovered heat: 313.318 GWh/year
Comparator emissions: 203,460 tCO2e/year
Project emissions: 11,185 tCO2e/year
Avoided operational emissions: 192,275 tCO2e/year
Operational reduction: 94.50%
Illustrative wind/solar generation: 901.047 GWh/year (267.167 MW wind + 89.056 MWp solar)
Annual net surplus: 46.977 GWh/year

RIVER SCREENING
Full-load facility heat boundary: 107.535 MW. The cumulative model uses the same NRFA gauge proxies and conservative instantaneous-mixing assumptions as V5, but reruns them with the V6 capacity schedule. At Bywell, 90% heat diversion yields a screening sensitivity of 0.057°C at mean flow and 0.418°C at Q95; approximately 97.6% diversion is required for an illustrative 0.1°C Q95 mixed-rise target. These values are not permits or site-specific discharge studies.

All capacities and outputs are concept-stage screening values. Land, grid connection, fibre, heat demand, flood risk, ecology, local river flow and regulatory approvals must be assessed site by site.