The project targets only settlements on the main North Tyne, South Tyne or combined River Tyne. The eight proposed nodes total 93.51 MW IT, sized at 4.46 kW per resident from a 20,966-resident 2021 Census population basis. Hexham now hosts a proposed data centre as well as the transport, grid and fibre-gateway role.
Real topography and georeferenced river-community markers. Main River Tynes are blue. Telecom routes are proposed connections, not surveyed alignments. Community markers do not establish selected plots or cooling permission.
| River community | Current population | Main river | Community context | IT capacity at 4.46 kW/person |
|---|---|---|---|---|
| Falstone | 215 (2021 Census) | North Tyne | Rural village | 0.96 MW |
| Bellingham | 1,255 (2021 Census) | North Tyne | Service village | 5.60 MW |
| Wark | 719 (2021 Census) | North Tyne | Riverside village | 3.21 MW |
| Barrasford | 788 (2021 Census) (Chollerton parish) | North Tyne | Riverside village | 3.51 MW |
| Chollerford | 711 (2021 Census) (Humshaugh parish) | North Tyne | River crossing | 3.17 MW |
| Haydon Bridge | 2,374 (2021 Census) (Haydon parish) | South Tyne | Rail-linked village | 10.59 MW |
| Hexham | 11,346 (2021 Census) | Tyne | Market town / rail hub | 50.60 MW |
| Corbridge | 3,558 (2021 Census) | Tyne | Town / rail link | 15.87 MW |
| Total | 20,966 residents | Three main river reaches | 8 communities / 8 proposed nodes | 93.51 MW IT |
IT capacity is sized at 4.46 kW per resident using the latest official 2021 Census parish/town-council population available for each active community. For the small settlements without a standalone census parish, Barrasford uses Chollerton parish and Chollerford uses Humshaugh parish, the smallest parish geographies covering those settlements. These are screening capacities: land, grid, fibre, heat customers, flood risk, river flow, ecology and permits still determine buildable size.

Using the two supplied Spanish site plans as design references, this screening plan adapts the concept to a North Tyne setting in British English. The screening centre shown is approximately 55.143° N, 2.251° W (about OS grid NY 841 832) near Bellingham and the B6320. It is a geographic screening reference only — not a selected parcel, land offer or planning application.
Northumberland's public flood studies identify wide areas beside the River North Tyne and Boat Road as Flood Zone 3. For that reason, the V6 concept places all major buildings on higher ground and reserves the river edge as a landscaped no-build floodplain/riparian buffer.
The plan combines an illustrative 5.60 MW rural data centre, a 20,000 m² high-tech greenhouse with purple red+blue LED light movers, recirculating prawn/aquaculture tanks, an approximately 5 MWp solar array, an alfalfa and hay dryer using recovered heat, thermal storage, a small biogas plant, EV charging/community vehicles and a grid connection compound.
The historic South of Bellingham development area used in public flood studies is only 2.9 ha and the Foundry Road employment area is much smaller, so this drawing is not a claim that the full campus fits either historic boundary. A real site would require landowner agreement, survey, planning review, site-specific flood modelling, ecological assessment, grid/fibre studies and any Environment Agency consents.
Public screening references: Northumberland Local Plan 2016–2036 and the Level 2 Strategic Flood Risk Assessment. The latter records the South of Bellingham screening area at grid reference 383955, 583169 and E02 Foundry Road at 384084, 583470.
Eight illustrative nodes total 93.51 MW at 4.46 kW per resident: Falstone 0.96, Bellingham 5.60, Wark 3.21, Barrasford 3.51, Chollerford 3.17, Haydon Bridge 10.59, Hexham 50.60 and Corbridge 15.87 MW IT. Dedicated dark fibre and a diverse route link the North and South Tyne branches through Hexham towards Newcastle. Synchronous AI training requires measured scale-across performance.
Distributed inference and data processing are straightforward candidates. Any claim of synchronous large-scale AI training across the valley would require measured latency, bandwidth and accelerator-fabric validation.
Kielder Water regulates the upper North Tyne. The South Tyne has a different catchment; both branches meet near Hexham before flowing past Corbridge. River cooling must use local flow and temperature evidence, not a downstream gauge as proof of upstream capacity.
The engineering preference is closed-loop cooling, high-recirculation greenhouse irrigation and recirculating aquaculture so that the project creates as little additional water demand as practical.
Before any site is selected, abstraction availability, ecological constraints, flood risk and discharge conditions would be checked with the Environment Agency and Northumbrian Water.

Winter greenhouse concept with the requested tracked horticultural lighting: large movable LED panels use a red-and-blue spectrum that appears purple, directly above the crop rows, while the landscape outside is snow-covered.
Liquid-cooled computing can provide a steady stream of low-temperature heat for greenhouses, aquaculture, district heating, hot-water pre-heating and crop drying.
Not every megawatt of heat will find a useful customer every hour. The design therefore matches temperature, seasonality, distance and thermal storage site by site.
The current screening model uses 854.1 GWh/year of project electricity and an illustrative wind/solar envelope of 901.0 GWh/year. Because generation and demand do not occur at the same hour, the useful number is not simply generation minus load.
On an annual energy balance the renewable envelope exceeds project demand by about 47.0 GWh/year, equivalent to roughly 5.4 MW average net export over a full year if grid export is available and curtailment is avoided.
The model also contains 85.4 GWh/year of unmatched grid imports. That implies approximately 132.4 GWh/year of generation occurring in hours when local output exceeds contemporaneous project load. A battery, flexible drying, EV charging and thermal storage can absorb part of that before the remainder is exported or curtailed.
That is about 10% of annual project electricity and is equivalent to roughly 880 full-load-equivalent hours at the network's average electrical load. It does not mean 880 literal grid-only hours: much of the import would be partial top-up while wind or solar is still producing.
Highest export periods: windy autumn/winter hours, strong spring and summer daytime solar, and any period when the battery and thermal stores are already charged and flexible loads such as crop drying, EV charging and greenhouse lighting cannot use the remaining generation.
Physical grid-only periods: calm nights, prolonged low-wind winter weather, maintenance or faults affecting local renewable plant, or intervals after the battery has reached its minimum reserve. The present annual model does not contain enough site-specific hourly weather data to publish a defensible number of literal grid-only hours; that requires chronological wind/solar traces and a dispatch simulation.
Battery bank: about 475 MWh usable / 150 MW discharge distributed across the eight sites. That is approximately four hours of normal facility demand after allowing for reserve and degradation, and much longer if non-critical greenhouse, drying and EV loads are shed.
Backup generation: site-level N+1 plant totalling roughly 135 MW across the network. The first renewable combustion layer is biogas/biomethane engine generation where stored gas is available; longer outages use dedicated HVO100 / certified renewable-diesel generator sets. Flexible thermal and agricultural loads are shed before IT load.
Operating sequence: grid-forming battery/UPS responds instantly; local renewables continue where available; biogas engines start next; renewable-diesel gensets carry a prolonged outage. The design does not require fossil gas or petroleum diesel.
These are concept-stage engineering estimates derived from the current annual model, not a grid-connection offer or completed chronological dispatch study. Export capacity, battery size, generator rating and fuel storage would be finalised only after DNO studies, protection design, actual hourly weather traces and site-specific load profiles.
All capacities on this page are concept-stage screening figures — not grid offers, abstraction licences, planning consents or construction commitments.
The Digital Gardens aims to demonstrate that geographically distributed AI factories can deliver useful computing while returning server heat to local food production and communities, setting a new standard for data centres.
NVIDIA Spectrum-XGS Ethernet extends Spectrum-X with scale-across networking to connect multiple data centres into a unified AI factory. The proposed dedicated dark-fibre optical fabric would carry that traffic between the eight riverside nodes; dark fibre is the physical carrier infrastructure, while NVIDIA supplies the networking technology.
The project would test distributed inference and training, collective-communication performance, end-to-end latency, bandwidth, resilience, heat use and carbon performance. Making conventional mega data centres obsolete is the demonstration goal. It has not yet been established by this proposed project, and no NVIDIA partnership or endorsement is implied.
NVIDIA Spectrum-X and Spectrum-XGS · NVIDIA technical explanation of scale-across networking

The river model follows the North Tyne through five nodes, adds Haydon Bridge on the South Tyne, then combines both branches before Hexham and Corbridge. Downstream sites retain the heat rejected upstream. At full IT capacity the total facility heat boundary is 93.508 × 1.15 = 107.535 MW.
| Station | Historical record | Mean flow | Q95 flow |
|---|---|---|---|
| Tyne at Bywell | 1956-10-01 to 2025-09-30 | 45.219 m³/s | 6.140 m³/s |
| North Tyne at Reaverhill | 1959-10-01 to 2025-09-30 | 22.406 m³/s | 3.007 m³/s |
| South Tyne at Haydon Bridge | 1962-10-01 to 2025-09-30 | 19.707 m³/s | 2.140 m³/s |
| North Tyne at Uglydub | 1982-05-01 to 2025-09-30 | 8.224 m³/s | 1.490 m³/s |
| Community | Upstream IT | Flow reference | All heat: mean / Q95 | 90% diverted: mean / Q95 |
|---|---|---|---|---|
| Falstone | 0.96 MW | North Tyne at Uglydub | 0.032 / 0.177°C | 0.003 / 0.018°C |
| Bellingham | 6.56 MW | North Tyne at Uglydub | 0.219 / 1.209°C | 0.022 / 0.121°C |
| Wark | 9.76 MW | North Tyne at Uglydub | 0.326 / 1.800°C | 0.033 / 0.180°C |
| Barrasford | 13.28 MW | North Tyne at Reaverhill | 0.163 / 1.213°C | 0.016 / 0.121°C |
| Chollerford | 16.45 MW | North Tyne at Reaverhill | 0.202 / 1.503°C | 0.020 / 0.150°C |
| Haydon Bridge | 10.59 MW | South Tyne at Haydon Bridge | 0.148 / 1.359°C | 0.015 / 0.136°C |
| Hexham | 77.64 MW | Tyne at Bywell | 0.472 / 3.474°C | 0.047 / 0.347°C |
| Corbridge | 93.51 MW | Tyne at Bywell | 0.568 / 4.184°C | 0.057 / 0.418°C |
ΔT = H × 10⁶ / (ρ × cₚ × F), using ρ = 1,000 kg/m³ and cₚ = 4,186 J/(kg·°C). H is residual cumulative heat in MW and F is the selected flow proxy in m³/s. The downloadable model includes 0%, 80% and 90% diversion sensitivities. Heat diverted elsewhere can be reused, stored temporarily, rejected by dry cooling, or avoided through computing-load reduction. The annual 50% use of captured IT heat in the carbon model does not imply 90% instantaneous diversion of facility heat.
Combined-Tyne screening: the full 93.51 MW network gives about 0.568°C at historical mean Bywell flow and 4.184°C at Q95 if all facility heat reaches water. With 90% diversion the estimates are 0.057°C and 0.418°C. These downstream values must not be applied to the smaller upstream North Tyne. The lower North Tyne’s five nodes total 16.45 MW, with 90%-diversion estimates of 0.020°C mean and 0.150°C Q95 using Reaverhill.
Uglydub measures releases below Kielder Dam and is used for the upper three nodes as an upstream-release sensitivity, omitting tributary inflows. This does not establish local intake flow or a guaranteed minimum. Barrasford and Chollerford use Reaverhill as a nearby lower-North-Tyne reference. Haydon Bridge uses its South Tyne gauge. Hexham and Corbridge use downstream Bywell as a cumulative comparison. Every intake and return still requires local flow, temperature, mixing, ecological and permit assessment.
For an illustrative 0.1°C fully mixed target, Bywell at Q95 would allow about 2.570 MW residual heat, requiring about 97.6% diversion of the complete full-load heat boundary. The lower North Tyne at Reaverhill Q95 allows about 1.259 MW for its 16.45 MW IT branch, requiring about 93.3% diversion. These are illustrative control targets, not approved permit conditions. Automatic low-flow and temperature limits must trigger alternative cooling or reduced load.
Complete instantaneous mixing and no heat loss to air are assumed. Near-field outfall plumes can be warmer. Q95 is a historical daily-flow percentile, not a guaranteed minimum, and daily records conceal short Kielder release pulses. River ecology, flood risk, maximum absolute water temperature and cumulative effects must be evaluated before selecting a parcel.
Flow snapshot: 12 October 2026; records end 30 September 2025. UKCEH NRFA API. Data from the UK National River Flow Archive.
Falstone, Bellingham, Wark, Barrasford and Chollerford directly border the main North Tyne. Haydon Bridge spans the South Tyne. Hexham and Corbridge sit on the combined Tyne. The 4.46 kW/resident sizing rule drives the proposed node capacity in each community, without claiming proved grid capacity, available land or ecological headroom. Buildings must be set back from flood-risk and riparian land while safe pipe routes reach permitted heat exchangers.
Kielder’s upstream location and the inland Tarset/Greenhaugh and Humshaugh village-centre pins are retained as wider-valley heritage, not active sites. Minor burns do not substitute for main-river flow evidence.
Download the canonical community and capacity schedule